North Ocean Shipping Co v Hyundai Construction Co (The Atlantic Baron)
A shipbuilder's demand for 10% more was economic duress, but the buyers lost the right to rescind by delaying for months.
- Citation
- [1979] QB 705
- Court
- High Court
- Year
- 1979
- Topic
- Economic duress
The facts
Hyundai agreed to build a tanker for a fixed price in US dollars. When the dollar was devalued, Hyundai demanded 10% more and threatened not to deliver. The buyers had a valuable charter lined up, so they agreed. They waited about eight months after delivery before claiming the money back.
The issue
Could the buyers recover the extra payment?
The decision
No.
Why it matters
An early recognition of economic duress, and the leading example of affirmation barring rescission.
Use it for
Use it to show that the victim must act promptly once the pressure ends.