Maredelanto Compania Naviera SA v Bergbau-Handel GmbH (The Mihalis Angelos)

An "expected ready to load" clause in a charterparty was a condition, so its breach allowed the charterers to end the contract.

Citation
[1971] 1 QB 164
Court
Court of Appeal
Year
1970
Topic
Contract terms and exclusion clauses

The facts

A charterparty (a contract to hire a ship) stated that the ship was "expected ready to load" about 1 July. When the statement was made, the owners had no reasonable grounds for believing the ship would be ready by then. The charterers cancelled the contract.

The issue

Was the clause a condition, allowing the charterers to end the contract?

The decision

Yes.

Why it matters

Shows courts treating a type of commercial term as a condition for the sake of certainty, despite Hong Kong Fir.

Use it for

Use it to show when a term will be classified as a condition, and with Bunge v Tradax for time clauses.