Project tools, teams and responsibilities: 10 questions

Print it for a lesson starter or homework. The answers are on a separate page.

The topic summary

  1. Training was budgeted at £5,000 but cost £6,500. What is this?

    1. An adverse variance of £1,500
    2. A favourable variance of £1,500
    3. A return on investment of 30%
    4. A critical path
  2. A project's IT costs were budgeted at £8,000 but came to £7,200. What is this?

    1. A favourable variance of £800
    2. An adverse variance of £800
    3. A critical path
    4. A tender
  3. What does "Gantt chart" mean?

    1. A bar chart showing a project's tasks against a timeline, so it is easy to see when each task happens, what overlaps and whether the project is on schedule.
    2. Information gathered first-hand for the research, through questionnaires, surveys, interviews, observation, focus groups and online communities.
    3. The three constraints on every project, scope, cost and time, with quality in the middle.
    4. A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks.
  4. What does "Critical path analysis" mean?

    1. BAILII (British and Irish Legal Information Institute) gives free online access to many judgments and some legislation.
    2. A document justifying a project before it starts: the problem, the options, the advantages, timescales, costs, return on investment and risks.
    3. When people oppose or delay change, often because they fear for their jobs, dislike new ways of working or do not understand why it is needed.
    4. A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks.
  5. What does "Project sponsor and project manager" mean?

    1. The project sponsor is a senior person who champions the project, provides funding and makes major decisions.
    2. An organisation that campaigns to influence government policy, businesses or public opinion on a particular issue.
    3. Writing that explains or comments on the law, such as textbooks, journal articles and practitioner guides.
    4. A published collection of important judgments.
  6. What does "Variance analysis" mean?

    1. A document justifying a project before it starts: the problem, the options, the advantages, timescales, costs, return on investment and risks.
    2. Comparing actual results with the budget.
    3. A list at the end of a piece of work of all the sources used, written in a consistent referencing format.
    4. A one-sided view that favours a particular position, often because the author has an interest in it.
  7. What does "Tendering" mean?

    1. When a trusted person or business recommends a client to a legal service, such as a satisfied client, an accountant or an estate agent.
    2. Legal work that involves a dispute, whether or not it reaches court, such as suing for money owed, an employment claim or a criminal defence.
    3. The government's own legal service, employing lawyers who advise government departments and represent them in court.
    4. A formal process in which organisations bid for a contract, usually by submitting a proposal and price that the buyer compares against others.
  8. What does "Stakeholder" mean?

    1. Anyone with an interest in, or affected by, what a business does.
    2. An organisation, such as a charity, that raises money and may make a surplus, but puts that surplus back into its social, environmental or cultural aims rather than…
    3. A tax on the profits of limited companies.
    4. A merger is when two businesses combine into one.
  9. A Gantt chart shows tasks over time; ____ finds the longest chain of dependent tasks.

    1. bAILII and legal databases
    2. critical path analysis
    3. project life cycle
    4. lewin's change model
  10. Budgets are monitored by ____: favourable if better than planned, adverse if worse.

    1. bAILII and legal databases
    2. variance analysis
    3. bias
    4. plagiarism

Answers

  1. A: An adverse variance of £1,500. Spending more than budgeted is an adverse variance.
  2. A: A favourable variance of £800. Spending less than planned is better than budget, so it is a favourable variance.
  3. A: A bar chart showing a project's tasks against a timeline, so it is easy to see when each task happens, what overlaps and whether the project is on schedule.. Gantt chart: A bar chart showing a project's tasks against a timeline, so it is easy to see when each task happens, what overlaps and whether the project is on schedule.
  4. D: A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks.. Critical path analysis: A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks. Any delay to a task on it delays the whole project.
  5. A: The project sponsor is a senior person who champions the project, provides funding and makes major decisions.. Project sponsor and project manager: The project sponsor is a senior person who champions the project, provides funding and makes major decisions. The project manager plans and runs it day to day.
  6. B: Comparing actual results with the budget.. Variance analysis: Comparing actual results with the budget. A favourable variance is better than planned (such as costs lower than budgeted); an adverse variance is worse.
  7. D: A formal process in which organisations bid for a contract, usually by submitting a proposal and price that the buyer compares against others.. Tendering: A formal process in which organisations bid for a contract, usually by submitting a proposal and price that the buyer compares against others.
  8. A: Anyone with an interest in, or affected by, what a business does.. Stakeholder: Anyone with an interest in, or affected by, what a business does. Internal stakeholders are inside the business (owners, managers, employees); external stakeholders are outside it (customers, suppliers,…
  9. B: critical path analysis. A Gantt chart shows tasks over time; critical path analysis finds the longest chain of dependent tasks.
  10. B: variance analysis. Budgets are monitored by variance analysis: favourable if better than planned, adverse if worse.